Report progress on your tasks without Microsoft Project

Open the plan your project manager published, report work or percent complete on your own assignments, and add a comment explaining it. The update goes back to the manager to accept.

  • No Microsoft Project licence
  • Report from any view
The Task Usage view in Seavus Project Viewer, with the Task Update tab in the ribbon

Report from the view you already read the plan in

Reporting happens in Seavus Project Viewer, against the plan the project manager published.

  • Task Usage. The work assigned to each task, day by day, where reporting time is the least work.
  • Resource. Your own assignments grouped together, so every task you report on is on one screen.
  • Gantt Chart. Report from the plan itself, with the schedule in view while you enter progress against a bar.

An update is more than a percent complete

  • Time worked on an assigned task, including more than the planned work, and overtime whether or not the manager planned it.
  • Time or progress for days in the past or ahead, outside the task’s own range.
  • Updates on tasks that have no assigned resource (unassigned tasks).
  • A comment on any update, so the reason travels with the number.

What a team member needs

No Microsoft Project licence, and nothing to install beyond the viewer.

  • Seavus Project Viewer, with Task Update. Installed on your machine. The Task Update tab sits in the ribbon, next to the views you read the plan in.
  • The plan, from your manager. The .mpp file the project manager published, on the shared folder both sides can read and write.
  • Nothing to configure. You report against the plan you were given; the manager accepts or rejects each update in Microsoft Project.

Questions from team members

Do I need Microsoft Project to report progress?

No. You report from Seavus Project Viewer with Task Update added. Only the project manager runs Microsoft Project and the Seavus add-in.

Does my update change the schedule straight away?

No. It is reported first; the project manager accepts or rejects it, and accepting applies the change to the .mpp file.

Can I report work I was not planned for?

Yes. You can report more work than planned, overtime the manager did not plan, and time on days outside the task’s range.

Can I say why an update changed?

Yes. Every update takes a comment, so the reason travels with the number instead of arriving separately by email.

Give every team member a way to report progress

Read-only access to the plan, plus a two-click update on the tasks they own.